PINEHURST SCHOOL

This project is the construction of a new library.  This is to be constructed between two existing buildings the gym/existing library and the arena.

The proposed time frame for this project is 9 months

 

 

 

 

 

 

 


TAKAPUNA PRIMARY SCHOOL

The project involves the conversion of 3 teaching spaces into a combined modern learning environment, the installation of new internal sliding doors to existing openings in the adjacent area and more general fire and security upgrades.

The project time frame is around 4 months


HOBSONVILLE SCHOOL — THIS PROJECT IS ON HOLD

The scope of work for this project is in two stages.  Stage 1 is Internal Alterations to the existing Library and Interior Alterations removing existing Interior Walls creating an open plan classroom with breakout space to Block 6.

Stage 2 is for a new Pool Toilet outbuilding plus general pool site works plus new external joinery and cladding to Northern Elevation, new toilets to Eastern Elevation. Internal walls removed and replaced with new portal frames.  All surfaces re-lined.  This is to be completed to Block 1.

Time frame for completion for both stages is 8 Months

AORERE COLLEGE

The scope of work for this project is in stages.

Demolition of existing office, storage, shed to South of existing gymnasium and replace with new weights room, office, accessible toilet, laundry and PE Sports storage.

Significant upgrade to Metal Work and Wood Work Rooms.

Refurbishment of upper level classrooms, staff and resource areas in Nelson A Block.  Addition of a new meeting space on ground level of Block A and student services centre.

Time frame for the completion of all works is 9 months

ROSEHILL COLLEGE

The scope of work for this project is for Major Special Needs Modifications at Rosehill College.  Works include a raised Unispan walkway bridge connecting S & C Blocks.  S Block lift shaft & Lobby areas.  C Block accessible ramp with landing and stair access.

Time frame for this project is completion in December 2018.

MANUREWA WEST SCHOOL

So that our schools and in good and safe physical condition the Ministry of Education have approved to upgrade Manurewa West School which is in need of desperate repair.

The re-development of this project is to demolish the existing 8 Classroom Block and construction of a new 2 Storey 12 Classroom. The additional classrooms will be utilised for projected roll growth  There is also additional car parking. .  This is an extensive project which has a 12 month time frame.

 

EAST TAMAKI SCHOOL

The scope of work for this project involves the Interior and Exterior refurbishment of existing D Block.

The first stages of this project will include partial demolition of existing buildings and structures to the extent necessary to carry out the contract works.

 

 

FORREST HILL AGED CARE

Great progress on this project.  Roof and windows are now in.  Internal framing is speeding ahead.  Project is on target to finish in June.