PINEHURST SCHOOL

The Pinehurst School Library is underway.  Foundations are being prepared

and progress is changing daily.  This build is between classrooms

and towards the rear end of the school.

 

 

 

 

 

 


TAKAPUNA PRIMARY SCHOOL

The project involves the conversion of 3 teaching spaces into a combined modern learning environment, the installation of new internal sliding doors to existing openings in the adjacent area and more general fire and security upgrades.

The project time frame is around 4 months


HOBSONVILLE SCHOOL — THIS PROJECT IS ON HOLD

The scope of work for this project is in two stages.  Stage 1 is Internal Alterations to the existing Library and Interior Alterations removing existing Interior Walls creating an open plan classroom with breakout space to Block 6.

Stage 2 is for a new Pool Toilet outbuilding plus general pool site works plus new external joinery and cladding to Northern Elevation, new toilets to Eastern Elevation. Internal walls removed and replaced with new portal frames.  All surfaces re-lined.  This is to be completed to Block 1.

Time frame for completion for both stages is 8 Months

AORERE COLLEGE

This project is moving along at a cracking pace.  With the first stage of the New Weights Room complete, we are now on to the New Tech Block.  Internal structures and pre-wiring is currently being completed.

 

New Tech Room


Complete Weights Room


New Weights Room


New Tech Room

 

ROSEHILL COLLEGE

The scope of work for this project is for Major Special Needs Modifications at Rosehill College.  Works include a raised Unispan walkway bridge connecting S & C Blocks.  S Block lift shaft & Lobby areas.  C Block accessible ramp with landing and stair access.

MANUREWA WEST SCHOOL

With a string of great weather, Ground Foundations have been poured and Ground Floor columns are being prepped for concrete.  This project is taking great shape.

 

EAST TAMAKI SCHOOL

The scope of work for this project involves the Interior and Exterior refurbishment of existing D Block.

The first stages of this project will include partial demolition of existing buildings and structures to the extent necessary to carry out the contract works.

 

 

FORREST HILL AGED CARE

Great progress on this project.  Roof and windows are now in.  Internal framing is speeding ahead.  Project is on target to finish in June.

 

HAURAKI PRIMARY SCHOOL

The project involves the upgrade of 2 existing classrooms, new external doors to 4 classrooms, the conversion of an existing cloak bay to a new group space, new bag storage boxes, internal glazing, the demolition of the existing boys toilet and the construction of new adjacent the existing girls toilets, as detailed on the drawings.

 

The time frame for this project is completion end of May